According to Alalam.ir Website : Ahmadian said in a statement Saturday, saying he was conducting the test on the turbine at 3,000 rpm, and we are now in the final phase where other tests are to reach higher than 3600 rpmAhmadian said that after a successful test on the turbine will be the final evaluation of the reactor, and then you will be preparing for the possibility of connecting electricity to the public network, indicating that the post-launch of nuclear plants need special studiesAhmadian said that in the forefront of the priorities of Iran's Atomic Energy Organization is to run the Bushehr nuclear power plant, and that the implementation of this project needs careful study, especially as it should be cautious and take into account all the issues expected to be take advantage of this golden opportunity in the right way ...